SAD33 PLUS / QC AC-FILLER 33

Go back to product info

Preparation

  • white or transparent window squeegee
  • brush
  • spade
  • thermometer
  • floor scraper
  • vacuum cleaner

Mixing

  • Check there is enough product available
  • Check the floor and air temperature: 5-30°C, ideal: 15-20°C
  • Remove protruding stones with a floor scraper
  • Blow or vacuum away the stones
  • Tape off baseboards or other boards

Mixing

  • Do not mix product to avoid air entrapment
  • There may occasionally be some condensation at the top of the bucket. Do not pour this moisture on the floor or mix it!

Clean tools

  • Pour 0.5-1 litre of product on the floor
  • Divide:
      • Spread the material over ±2 m wide and a strip of ±60 cm
      • spread from left to right and right to left
      • hold the squeegee blade ±45° to the floor
      • overlap the previous strip by 50% at the start of each new strip
      • Check all the pores have been filled
      • Spread again if necessary
  • Wiping:
      • necessary to remove excess product and avoid streaking
      • Use light pressure back to front
      • Lift the squeegee each time and remove the excess material from the squeege
      • Squeegee blade at ±25° relative to floor

Additional points of attention

  • half-empty packaging: the material can still be stored in closed packaging for the next project, otherwise dispose of as chemical waste.
  • Empty packaging: cured material can be removed quite easily from the buckets, it is then considered to be construction waste. Doing this means the buckets can still be reused.
  • Clean tools with water

Disclaimer

  • to avoid streaks the edges must be kept wet at all times. For large floors it is recommended to work with several people.
  • If possible, it is recommended to work in parallel to the largest/lowest windows (to make streaking less visible)
  • Attention: Do not use for outdoor applications
  • Avoid high floor temperatures :
      • Adjust underfloor heating to ±15°C 1 to 3 days in advance
      • Tape up windows if the sun is shining through
  • Avoid large temperature differences:
      • Turn off or remove air conditioning units that are blowing on the floor
  • Sufficient ventilation without creating drafts on the surface
  • Do not use a brush, roller or squeegee. Only use a small flat brush in inaccessible places
  • Only for new marble or stone carpet and certainly do not work on damp substrates

 

Video

 

 

Disclaimer

These brief installation instructions are provided to help you quickly get started with the installation. However, it is important to first read the technical data sheet and to take note of the safety data sheets Both documents can be found at the bottom of this page under downloads.

Downloads

Public downloads

  🇳🇱 🇫🇷 🇬🇧 🇩🇪
TDS

NL

FR

EN

DE

MSDS

NL

FR

EN

DE

Contact our Sales Team and order now.

Contact our Sales Team and order now.